Bryn Mawr Senior Housing/2800 Wayzata Office
Proposed Timeline
**Housing Schedule subject to 2020 funding. Office may advance earlier
TASK COMPLETION
AHIF/TOD Application 2/1/2020
City pre-DEED Grant Application Due 1/18/2020
City pre-LCDA Grant Application Due 2/15/2020
AHIF Award 4/30/2020
DEED/TBRA/Hennepin County Grants Application Due May, 2020
LCDA Grant Application Due June, 2020
City AHTF Application 6/1/2020
MHFA Application June, 2020
DEED/TBRA/Hennepin County Grant Award June, 2020
Project Design (DD) 6/1/2020
Bond Authority / Grant Resolutions Date August, 2020
Bond / 4% Tax Credit Application August, 2020
TIF Application August, 2020
City AHTF Award 10/1/2020
MHFA Award October, 2020
LCDA Grant Award October, 2020
MHFA issuance of HIB Bonds September, 2021
Closing October, 2021
Building Permit October, 2021
Construction Start November, 2021
Construction Completion 11/1/2022
Occupancy (Move-In) December, 2022
100% Occupied May, 2023